Home › Forums › PMP Questions and Answers Discussion › PMP Question 25 This topic has 1 reply, 1 voice, and was last updated 5 years, 1 month ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts March 7, 2020 at 1:04 PM #4792 adminKeymaster The sponsor has informed you that the resources for your project will be cut. The sponsor will want to know how long the project will take if only nine resources each month are committed to your project. What is this activity called? A Crashing B Floating C Leveling D Fast tracking March 7, 2020 at 1:06 PM #4793 adminKeymaster The correct answer is C. Resource leveling refers to keeping the number of resources the same and letting time and cost be flexible. Pass PMP in the First Attempt : PMP Strategy Revise PMP Concepts: PMP Concepts Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In