    Over the last few weeks, the team has made three changes to the activities on the project. The project manager must be more careful to?

    a) Record all the changes
    b) Provide documentation on all the changes to the sponsor
    c) Make sure the changes are reflected in the project scope baseline
    d) Prevent more changes from occurring

    #4701
    admin
    Keymaster

    The correct answer is C.

    This is a question with more than one right answer. The question is really asking which is MOST important. The easiest way to deal with these questions is to look for the choice that will have the biggest impact on the project. Choice A is important, but look again at choice C. It is a method of recording the change, like choice A, but it is more specific and detailed. Be careful about choices like D. Changes are not bad and should not generally be prevented.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.