You are a project manager for a product development project that has four levels in the work breakdown structure, and has been sequenced using the arrow diagramming method. The activity duration estimates have been received. What time management activity would you do NEXT?
A Duration compression
B Collect historical records from previous projects
C Create an activity list
D Under the work breakdown structure
The question is really asking, “What is done after Estimate Activity Durations?” All of the activities listed except choice A are done before Estimate Activity Durations.