Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #4669
    admin
    Keymaster

    You are a project manager for a product development project that has four levels in the work breakdown structure, and has been sequenced using the arrow diagramming method. The activity duration estimates have been received. What time management activity would you do NEXT?

    A Duration compression
    B Collect historical records from previous projects
    C Create an activity list
    D Under the work breakdown structure

    #4671
    admin
    Keymaster

    The correct answer is A.

    The question is really asking, “What is done after Estimate Activity Durations?” All of the activities listed except choice A are done before Estimate Activity Durations.

    Pass PMP in the First Attempt : PMP Strategy

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.