    Which of the following risk events is Most likely to interfere with attaining a project’s schedule objective?

    a) Delays in obtaining required approvals
    b) Substantial increases in the cost of purchased materials
    c) Contract disputes that generates claims for increased payments
    d) Slippage of the planned post implementation review meeting

    #4167
    admin
    Keymaster

    The correct answer is A.

    Cost increases (choice B) and contract disputes (choice C) will not necessarily interfere with schedule. Notice the words “post-implementation” in choice D. It will not definitely interfere with the project schedule. Choice A is the only one that deals with a time delay.