    Another project manager in your company is having difficulty managing his project. You have found that he has not used a project charter and that is probably the cause of the problem. How can you help?

    a) Provide him with a copy of an article about project charters
    b) Work with his boss to get him a mentor
    c) Develop a draft project charter for his use
    d) Talk to him about his project and offer help in creating a project charter

    #2233
    admin
    Keymaster

    The correct answer is D.

    You should offer your assistance without doing the work.