Home Forums PMP Questions and Answers Discussion Integration Management Question 3

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #1778
    Gary
    Guest

    Which of the following BEST describes the difference between Control Scope process and Perform Integrated Change Control Process?
    a) Control scope focuses on making the changes to the product scope and Perform Integrated Change Control focuses on making changes to integration
    b) Control scope focuses on controlling the scope of the project and Perform Integrated Change Control focuses on determining the impact of the change of scope on cost, time, quality, risk.
    c) Control scope focuses on controlling the scope of the project and Perform Integrated Change Control focuses on making changes to integration
    d) Control scope focuses on making the changes to the product scope and Perform Integrated Change Control focuses on determining the impact of the change of scope on cost, time, quality, risk.

    #1779
    Gary
    Guest

    The correct answer is B.

    Notice how the choices are similar to each other? Simply look at the first part of each choice “Control Scope focuses on ?” and see which of the two versions of the first part of the statement is correct. This eliminates choices A and D. Then read the second part of each choice. Choice C is partially correct and partially incorrect. Only choice B is completely correct.

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.