    Which of the following would be the MOST appropriate thing to do during the executing process group?

    a) Forecast when the next milestone will be completed
    b) Recommend updates to the Project Management Plan
    c) Recalculate how long the project will take
    d) Determine if project controls needs to be updates

    #2377
    admin
    Keymaster

    The correct answer is B.

    Only choice B occurs during the executing process group. Choices A, C, and D occur in monitoring and controlling.