    All of the following are purposes of project charter except?

    a) It establishes the project
    b) It identifies the product acceptance criteria
    c) It gives the project manager authority
    d) It includes stakeholder’s requirements

    #2349
    admin
    Keymaster

    The correct answer is B.

    Product acceptance criteria is included in the project scope statement.