    The project was working well until the director of marketing discovered that two of her staff members were working on different versions of the sampling plan, a product of your project. Which of the following BEST describes what needs the attention of the project manager on this project?

    a) Stakeholder Management
    b) Resource allocation
    c) Staffing management plan
    d) Configuration management

    #5612
    admin
    Keymaster

    Correct answer is d.

    Configuration Management maintains different versions of the documents and helps in ensuring everyone is working on the same version.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    #5613
    Emenike Emenike
    Participant

    Are Questions in the Knowledge Areas updated from time to time. I need to know so that I have to re-try them from time to time.

    #5621
    admin
    Keymaster

    Questions are updated but not frequently. I publish whenever it gets updated.