    When should the project baselines be changed?

    I thought only when CCB approves, we can change it. Can you please explain the answer.

    #2242
    admin
    Keymaster

    You are correct. Baselines can be changed only after changes are approved from the CCB. Once approved, PM needs to perform 4 duties:
    1. Update Project Management Plan
    2. Inform concerned stakeholders
    3. Give to the execution for development
    4. Write lessons learned in OPAs

Viewing 2 posts - 1 through 2 (of 2 total)