    please let me know details on the question answer below

    thanks
    You are a project manager on a project that requires 100 items to be tested, spaced evenly over 5 weeks. You have just begun week 3 , with an overall budget of US$10,000. To date you have spent US$2000 with 40 items tested successfully. What does the Cost Variance (CV) tell you during this time?
    Project is on budget
    Project is getting $2 of the work for every dollar spent
    Project is $2000 under budget
    The project is proceeding at 100% of the expected rate

    #3245
    admin
    Keymaster

    The correct answer is C.

    EV is determined from a total budget of $10,000 and a five week duration. Each week would be $2,000. Therefore, for two weeks of completed work, we have an EV of $4,000. CV = EV – AC, CV = $4000 – $2000 = $2,000. Positive means you are under budget.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Cost Management Concepts: Project Cost Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.