Home Forums PMP Questions and Answers Discussion Cost Management Question 7

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2237
    admin
    Keymaster

    Project set up costs are an example of?

    a) Variable costs
    b) Fixed costs
    c) Overhead costs
    d) Opportunity costs

    #2238
    admin
    Keymaster

    The correct answer is B.

    Setup costs do not change as production on the project changes. Therefore, they are fixed costs.

    Revise Cost Management Concepts: Project Cost Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.