Home › Forums › PMP Questions and Answers Discussion › Cost Management Question 7 This topic has 1 reply, 1 voice, and was last updated 5 years, 7 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts September 26, 2019 at 3:26 AM #2237 adminKeymaster Project set up costs are an example of? a) Variable costs b) Fixed costs c) Overhead costs d) Opportunity costs September 26, 2019 at 3:31 AM #2238 adminKeymaster The correct answer is B. Setup costs do not change as production on the project changes. Therefore, they are fixed costs. Revise Cost Management Concepts: Project Cost Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In