  • #2210
    admin
    Keymaster

    A project has a team member assigned to the project full time. What is the MOST likely affect on the project if that resource completes her activity sooner than planned?

    a) Lower quality deliverables
    b) Wasted cost
    c) A subsequent activity will be delayed
    d) Changes to the risk response plan

    #2211
    admin
    Keymaster

    The correct answer is B.

    A full-time team member who completes her work sooner than planned could be forced to wait for the start of her next activity. Since she is full time, she would have to be paid for time not working.

    Revise Cost Management Concepts: Project Cost Management