    All of the following are components of cost management EXCEPT?

    a) Vendor bid analysis
    b) Analogous estimating
    c) Earned value management
    d) Estimate activity resources

    #3284
    admin
    Keymaster

    The correct answer is D.

    Vendor bid analysis (choice A) and analogous estimating (choice B) are tools for Estimate Costs. Earned value management (choice C) is a part of performance measurement analysis in Control Costs. By the process of elimination, Estimate Activity Resources is the correct response. It is part of resource management.