    What type of cost is team training?

    a) Direct
    b) NPV
    c) Indirect
    d) Fixed

    #3160
    admin
    Keymaster

    The correct answer is A.

    You are training the team on skills required for the project. The cost is directly related to the project and thus a direct cost.