Home › Forums › PMP Questions and Answers Discussion › Cost Management Question 16 This topic has 1 reply, 1 voice, and was last updated 5 years, 5 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts November 2, 2019 at 6:40 PM #2488 adminKeymaster The difference between the cost baseline and the cost budget can be BEST described as? a) The management reserve b) The contingency reserve c) The project cost estimate d) The cost account November 2, 2019 at 6:48 PM #2490 adminKeymaster The correct answer is A. Cost accounts are included in the project cost estimate, and the contingency reserve is added to that to come up with the cost baseline. Thereafter, the management reserve is added to come up with the cost budget. Pass PMP in the First Attempt : PMP Strategy Revise Cost Management Concepts: Project Cost Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In