Home Forums PMP Questions and Answers Discussion Cost Management Question 14

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2443
    admin
    Keymaster

    During project executing, a new project manager is assigned to the project and finds that the activity cost estimates for the project have rarely been accurate. Which of the following was
    MOST probably not done?

    a) Obtain a cost constraint from the management , create a work breakdown structure, and develop a project management plan
    b) Obtain a cost constraint from the management, perform a risk assessment and form a team
    c) Form a team, create a work breakdown structure and use historical records from previous projects.
    d) Form a team, develop a project management plan and perform a risk assessment

    #2444
    admin
    Keymaster

    The correct answer is C.

    To find the answer, look for things that would cause a poor estimate. A project management plan (choices A and D) comes after the creation of estimates. Risk assessments (choices B and D) normally occur after estimating.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Cost Management Concepts: Project Cost Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)