Home › Forums › PMP Questions and Answers Discussion › Cost Management Question 11 This topic has 1 reply, 1 voice, and was last updated 5 years, 6 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts October 15, 2019 at 6:50 AM #2378 adminKeymaster All of the following are relevant for analyzing a cost overrun except? a) Labor rates b) Resources used c) Communication management plan d) Lag October 15, 2019 at 6:52 AM #2379 adminKeymaster The correct answer is D. Labor rates (choice A), resources used (choice B), and poor communications (choice C) could all have contributed to the cost overrun. Lag relates to waiting time. Revise Cost Management Concepts: Project Cost Management Quiz: 20 Questions Challenge 50 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In