Home Forums PMP Questions and Answers Discussion Cost Management Question 11

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2378
    admin
    Keymaster

    All of the following are relevant for analyzing a cost overrun except?

    a) Labor rates
    b) Resources used
    c) Communication management plan
    d) Lag

    #2379
    admin
    Keymaster

    The correct answer is D.

    Labor rates (choice A), resources used (choice B), and poor communications (choice C) could all have contributed to the cost overrun. Lag relates to waiting time.