    A project manager is trying to make a complex project at 6 sigma level with 15 people. The
    project manager decides to use a trend report because this will help him to?

    a) Evaluate earned value
    b) Examine project results over time
    c) Analyze the level of project complexity
    d) Determine the level of quality

    #2356
    admin
    Keymaster

    The correct answer is B.

    This is a wordy question; expect longer. Trends are found by comparing current to a baseline. A trend report shows areas needing attention based on the time analysis.