    You are the project manager for a large installation project when you realize there are over 200 potential stakeholders on the project. Which of the following would be the BEST course of action for you to take?

    a) Eliminate some stakeholders
    b) Contact your manager and ask which stakeholders are most important
    c) Gather the needs of all the most important stakeholders
    d) Find an effective way to gather the needs of all the stakeholders

    #2213
    admin
    Keymaster

    The correct answer is D.

    You need to consider the needs of all your stakeholders.