    The project has been working through some difficult technical issues relating to how the work should be done. The most recent problem related to the way each test was to be completed. There have also been disagreements with 2 of the 8 managers and the sponsors had to intervene once. The testing work is done when the project manager discovers that one of the changes agreed to has not been adequately completed. What did the project manager NOT do?

    a) Ask those doing the work to describe the change, to make sure they understood it.
    b) Get the sponsor to sign off on the change
    c) Make sure the functional manager closely supervised the training
    d) Provide more training for those during the testing

    #2013
    admin
    Keymaster

    The correct answer is A.

    The company change process or change control board would control whether or not the sponsor needed to sign the change in this situation (choice B). Nothing in the question or the field of project management could lead you to believe that choices C or D are necessary. Only choice A gets to the root of the problem.

    Pass PMP in the First Attempt : PMP Strategy

    All PMP Question & AnswersQuestion & Answers

    Revise PMP ConceptsPMP Concepts

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.