    If a project manager wants to report on an actual project results V/s planned results, what does he
    should use?

    a) Trend report
    b) Forecasting report
    c) Status report
    d) Variance report

    #3635
    admin
    Keymaster

    The correct answer is D.

    This situation describes the need to “compare.” A trend report (choice A) shows performance over time. A forecasting report (choice B) looks only to the future. A status report (choice C) is generally static (relating to a moment in time). The only choice that compares project results is a variance analysis (choice D).