Stakeholders can be identified in which project management process group?
a) Initiating, planning, executing, monitoring and controlling, closing
b) Initiating & Planning
c) Planning and Monitoring and controlling
d) Monitoring and controlling and closing
Stakeholders can be identified throughout the project management process groups. However, the earlier stakeholders are identified, the better for the project. If all of the stakeholders’ needs and requirements are taken into account before plans are finalized and project work is begun, fewer changes will be needed later in the project, when they will be more costly.