The project manager is having a very difficult time in keeping the project schedule on track. The project requires 220 people to complete it. All of the project problems have been fixed to the project manager’s satisfaction, the schedule performance index (SPI) is currently 0.67. The CPI is 1.26. There are 23 activities on the project and the PERT duration is 26. Under these circumstances , the monthly status report should report:-
a) That the project is doing well
b) That the project will be late
c) That the project cost is behind budget
d) The issues and options