    The project manager is having a very difficult time in keeping the project schedule on track. The project requires 220 people to complete it. All of the project problems have been fixed to the project manager’s satisfaction, the schedule performance index (SPI) is currently 0.67. The CPI is 1.26. There are 23 activities on the project and the PERT duration is 26. Under these circumstances , the monthly status report should report:-

    a) That the project is doing well
    b) That the project will be late
    c) That the project cost is behind budget
    d) The issues and options

    #2503
    admin
    Keymaster

    The correct answer is D.

    The professional and social responsibility of the project manager requires that the truth be told. Choice A is lying and unethical. Choice B is not the correct choice because you do not KNOW the project will be late. There is time to fix the problems. Choice C is not correct because there are no cost problems illustrated in the question. As in any report, you need to state the issues and options.

    Pass PMP in the First Attempt : PMP Strategy

    Revise Communication Management ConceptsProject Communication Management

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.