    A project team includes 5 people when the project manager adds two more, how many additional channels of communication are there?

    a) 7
    b) 10
    c) 21
    d) 11

    #2470
    admin
    Keymaster

    Correct answer is D.

    Previous communication channels = n*(n-1)/2 = 5*(5-1)/2 = 10

    New communication channels = n*(n-1)/2 = 7*(7-1)/2 = 21

    Additional channels = 21 – 10 = 11