PMBOK Pg No. 123. it’s clearly mentioned that- Measuring stakeholder satisfaction is the last activity but in integration management (20 questions) shows Release resources is the last activity. pl explain why.
Thanks for raising the query.
Please read page 123 carefully. It is written “The activities necessary for the administrative closure of the project or phase include but are not limited to:”.
Moreover, it is not in the specific order. It is simply the list.