During the first iteration, the team estimated to complete 5 user stories. Development part of each user story is estimated at 3 story points and testing part is estimated at 2 story points. By the end of the iteration, team developed and tested 4 user stories and developed the fifth user story but could not test it. What was your team’s velocity for the first iteration?