Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #8614
    admin
    Keymaster

    During the first iteration, the team estimated to complete 5 user stories. Development part of each user story is estimated at 3 story points and testing part is estimated at 2 story points. By the end of the iteration, team developed and tested 4 user stories and developed the fifth user story but could not test it. What was your team’s velocity for the first iteration?

    a. 15
    b. 20
    c. 23
    d. 25

    #8617
    admin
    Keymaster

    Correct answer is B.

    In Agile, velocity is calculated on basis of completed user stories. Impartial work doesn’t contribute towards the velocity.

    World of Project Management : Mobile App

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.