    You join as a Scrum Master to new Scrum Team; you notice that the team is spending too much time in the product backlog refinement, and it is affecting their commitment towards the Sprint. How would you address this issue?

    A) Do nothing as the team discovered that refinement is very valuable to them
    B) Ask product owner to take the responsibility of refining the backlog items and let the Development Team focus on current sprint goals
    C) Cancel all refinement meetings until team start meeting commitments
    D) Coach team members to spend just enough time to refine the backlog for upcoming Sprint and focus on meeting the commitment of the Sprint.

    #5537
    admin
    Keymaster

    Correct answer is D.

    In agile, team follows progressive elaboration. In this, we refine only those items in detail that we are going to do next or in near future.