    Generally on an Agile project, who can provide the best estimation of the tasks?

    a. Development Team
    b. Product Owner
    c. Scrum Master
    d. Subject Matter Expert

    #7563
    admin
    Keymaster

    Correct answer is A.

    Since Development Team executes tasks so they are the closest to the technical details of the project. They can best provide the estimation regarding size and time required to complete the tasks.