    An Agile team faced critical security issue in their ongoing project. Similar issue was faced by the company in the other project in the past. What approach should the team follow in this situation?

    a. As all projects are unique so the team should work on new solution from the scratch to cover all scenarios
    b. Team should reuse the solution implemented in the other project and make necessary changes
    c. Team should outsource the solution and continue to work on other parts of the project
    d. Team should park the issue and handle it later, if its probability or impact increases

    #7558
    admin
    Keymaster

    Correct answer is B.

    Alistair Cockburn has defined success strategies in which one of the strategy is copy and alter. This helps in having a working framework to start with and avoids blank page syndrome.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.