    Sara, an Agile Coach, was explaining the importance of Burn charts to the team. She explained how burn charts can be useful in tracking down team’s performance. Which of the following statements about burn charts is wrong?

    a. Burndown chart goes down whereas Burnup chart goes up
    b. Burndown chart shows remaining work whereas Burnup chart shows completed work
    c. Burndown chart shows scope changes whereas Burnup chart doesn’t
    d. Burndown chart doesn’t shows scope changes whereas Burnup chart shows it

    #7505
    admin
    Keymaster

    Correct answer is C.

    Burnup charts maps both total work and work completed. In case of scope changes, that work is reflected in the total work.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.