    In Agile, velocity helps to know how much team can accomplish in future iterations. Which of the following is NOT true about velocity?

    a. It measures team’s capacity for work per iteration
    b. It varies the most during the first few iterations
    c. It stabilizes after few iterations
    d. It always increases with time as the team members get habitual of working with each other

    #7498
    admin
    Keymaster

    Correct answer is D.

    Velocity gets stabilized with time as team needs to maintain, refactor, and support already developed and deployed solutions. Moreover, sometimes team adds some improvement activities decided in retrospective meetings in the iteration which also let team pick up fewer story points for the iterations.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.