    Company ABC decided to execute Project XYZ through Kanban. Team leader was explaining how does Kanban works and helps in project exexution. He explained the flow of work items in Kanban. Which of the following is correct?

    a. All team members are assigned tasks in the starting and they complete it one by one
    b. Team leader assigns new task to members when they complete their existing tasks
    c. When any task is completed then the new task is pulled from previous stage into that stage of the process
    d. Scrum Master assigns new task to the team members

    #7476
    admin
    Keymaster

    Correct answer is C.

    Kanban has pull system. Whenever any task is completed, new task is pulled from the previous stage and added into that stage.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.