Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #7467
    admin
    Keymaster

    In the retrospective meeting, an Agile team discussed few improvement points. They implemented those points it in the next sprint. This helped the team to increase the amount of work they were doing in the given period of time. Out of the followings what would not be the reason for it?

    a. Duration to complete the work is reduced
    b. Amount of work being done is increased
    c. New members are added to the team
    d. Smaller user stories are picked

    #7469
    admin
    Keymaster

    Correct answer is D.

    Cycle Time = WIP / Throughput. Throughput can be increased by increasing WIP or decreasing Cycle Time or adding more members to the team so that more work can be done in the given period of time. Size of user stories doesn’t matter as team will be able to complete story points corresponding to their velocity in the sprint.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.