    Product owner along with agile team is priortising the work items. Which of the following items will be developed first?

    a. Business benefit $3000 and cost of development $1500
    b. Business benefit $3000 and cost of development $1000
    c. Business benefit $5000 and cost of development $4000
    d. Business benefit $5000 and cost of development $6000

    #7179
    admin
    Keymaster

    Correct answer is B.

    In Agile, higher business value item is developed first. Value based analysis helps in deciding true business value after factoring in development cost. In the question, option B has the business value of $3000 – $1000 = $2000, which is highest among all the options.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

    Study Groups: Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.