  • #7092
    admin
    Keymaster

    Systems thinking approach categorize projects in terms of their complexity mainly in two areas: project requirements and technological approach. In which of the following scenario, Agile works best?

    a. Requirements and Technology both are clear
    b. Requirements and Technology both are ambiguous
    c. There is some uncertainty in both Requirements and Technology
    d. Requirements are clear but Technology is ambiguous

    #7094
    admin
    Keymaster

    Correct answer is C.

    Agile works best when there is some uncertainty in both requirements and technology. If both are highly uncertain then Agile would not work in that case.

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMI-ACP Question & AnswersQuestion & Answers

    Learn Agile Concepts : Agile Concepts

    Agile Tips & Tricks : Agile Tips & Tricks

    Quiz:
    20 Questions Challenge
    50 Questions Challenge

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.