  • #7031
    admin
    Keymaster

    Team ABC is working on the Product XYZ. It is finished and the team asks few outsiders to try out the product while its members observe how users are interacting with it. What type of testing team is performing?

    a. Usability testing
    b. Exploratory testing
    c. Product testing
    d. Adhoc testing

    #7034
    admin
    Keymaster

    Correct answer is A.

    This is Usability testing. In this type of testing team tries to see how and user interacts with the solution in the realistic situation and tries to uncover problems that might need some changes.