    Sebastian is a scrum master handling the team that is working on an agile project. The team members complaints that their work is being delayed as the new sponsor (who doesn’t know about the agile methodology and practices) keeps on asking them about the project details every time. What would you do in this situation as a scrum master?

    A. Discuss with the product owner and request him to help in dealing with the new sponsor
    B. Contact the sponsor and request him to bring all the questions to you (scrum master) only
    C. Discuss with the team and fix one member as the spokesperson for the sponsor
    D. Tell the team to take his (scrum master) permission before having any discussion with the sponsor

    #5506
    admin
    Keymaster

    Correct answer is B.

    This is the responsibility of the Scrum Master.