Agile Question 560

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28555
    admin
    Keymaster

    During a sprint review, leadership praises the team for a big jump in velocity shown in the burnup chart. However, the Scrum Master notices that the total scope line has also increased significantly during the same period.

    What is the most likely explanation for this mismatch?

    A. The team adjusted estimates after completing the stories
    B. New backlog items were added and closed in the same sprint
    C. The team inflated story points to show better performance
    D. Scope was split into smaller items without changing totals

    #28558
    admin
    Keymaster

    ✅ Correct Answer: B. New backlog items were added and closed in the same sprint

    🔍 Explanation:
    A. The team adjusted estimates after completing the stories
    ❌ This might affect story point totals but doesn’t directly cause a simultaneous rise in both scope and completed work lines.

    B. New backlog items were added and closed in the same sprint
    ✅ Correct – Adding and finishing new scope mid-sprint raises both total scope and completed work in the burnup, creating the illusion of improved velocity without actual capacity growth.

    C. The team inflated story points to show better performance
    ❌ Would artificially boost velocity but wouldn’t explain the scope line increase in the burnup chart.

    D. Scope was split into smaller items without changing totals
    ❌ Changing item size affects backlog structure but not the total scope trend in a burnup chart.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    4 PMI-ACP Situational based Practice Tests : PMI-ACP Test Series

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.