✅ Correct Answer: C. Use collaborative discussion to reassess prioritization
🔍 Explanation:
A. Proceed as prioritized; raise scalability risk post-sprint
❌ This delays addressing a risk that could become more costly later.
B. Let PO decide; team executes without further debate
❌ Ignores the team’s expertise and undermines cross-functional decision-making.
C. Use collaborative discussion to reassess prioritization
✅ Reflects Agile principles—transparency, shared ownership, and valuing both business and technical input.
D. Ask Scrum Master to log the technical risk for review
❌ The Scrum Master can facilitate but not log or prioritize backlog items.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 PMI-ACP Situational based Practice Tests : PMI-ACP Test Series
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram