Agile Question 553

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28526
    admin
    Keymaster

    You’re working with a cross-functional Agile team building an e-commerce platform. During release planning, a senior stakeholder pushes to include every backlog item marked as “High Priority” in the first release. The team estimates this will take 5 sprints and may compromise quality due to time constraints.

    What is the best approach in this situation?

    A. Follow stakeholder’s request and aim to deliver all items
    B. Split high-priority items across releases based on business value
    C. Ask the product owner to reassign priorities to lower some items
    D. Extend sprint duration to accommodate all requested features

    #28529
    admin
    Keymaster

    ✅ Correct Answer: B. Split high-priority items across releases based on business value

    🔍 Explanation of Options:
    A. Follow stakeholder’s request and aim to deliver all items
    ❌ Incorrect. This ignores capacity, risks burnout, and delays value delivery. Agile favors incremental value and sustainable pace.

    B. Split high-priority items across releases based on business value
    ✅ Correct. Agile release planning emphasizes frequent delivery of the most valuable functionality. Break up features to release earlier, collect feedback, and adjust future work accordingly.

    C. Ask the product owner to reassign priorities to lower some items
    ❌ Incorrect. Reprioritization may be helpful, but the issue is not just priority—it’s delivery timing. Business value and release cadence must be considered.

    D. Extend sprint duration to accommodate all requested features
    ❌ Incorrect. This violates Agile principle of consistent sprint lengths for rhythm and predictability. Better to plan over multiple sprints.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    4 PMI-ACP Situational based Practice Tests : PMI-ACP Test Series

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.