Agile Question 55 Home › Forums › Agile (PMP/ACP/Scrum) Questions and Answers › Agile Question 55 This topic has 1 reply, 1 voice, and was last updated 5 years, 8 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts July 4, 2020 at 3:22 AM #6839 adminKeymaster An agile team wants to do some experiment to learn about newp approach What technique they should use? a. Iteration 0 b. Iteration H c. Sprint d. Spike July 4, 2020 at 3:27 AM #6842 adminKeymaster Correct answer is D. Spikes are of short duration cycles which developmemt team use to learn new approach and gain knowledge about something. Pass PMI-ACP in the First Attempt : PMI-ACP Strategy All PMI-ACP Question & Answers: Question & Answers Learn Agile Concepts : Agile Concepts Agile Tips & Tricks : Agile Tips & Tricks Quiz: 30 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Please enter an answer in digits:2 × 1 = Log In