✅ Correct Answer: B. Facilitate a value-based prioritization discussion
🔍 Explanation:
A. Ask the Scrum Master to mediate the conflict
✔️ Helpful if needed later. The Scrum Master may help facilitate, but resolving prioritization conflicts is primarily the Product Owner’s responsibility.
B. Facilitate a value-based prioritization discussion
✅ Best first step. The Product Owner should engage both stakeholders in a structured conversation focused on business value, customer impact, and outcomes—bringing objectivity to conflicting views.
C. Remove one stakeholder from decision-making
❌ Incorrect. Excluding stakeholders damages trust and limits collaboration. It may escalate the conflict and hurt long-term stakeholder engagement.
D. Proceed with planning using previous sprint goals
❌ Incorrect. Avoiding the issue doesn’t solve the conflict. Reusing old priorities without alignment may lead to waste and misalignment with business needs.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 PMI-ACP Situational based Practice Tests : PMI-ACP Test Series
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram