✅ Correct Answer: C. Work was not continuously integrated
🔍 Explanation:
A. Tasks were underestimated
❌ Incorrect. Underestimation would show slow or incomplete progress overall—not necessarily a late sprint spike.
B. Team ignored definition of done
❌ Incorrect. While possible, there’s no direct evidence from the burndown alone. Other metrics or reviews would indicate this more clearly.
C. Work was not continuously integrated
✅ Correct. A sudden drop near the end often means work wasn’t integrated or tested incrementally—violating continuous delivery practices and risking quality.
D. Velocity will likely increase next sprint
❌ Incorrect. Burndown trends don’t predict future velocity directly, especially if the team is not completing work steadily.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 PMI-ACP Situational based Practice Tests : PMI-ACP Test Series
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram