Agile Question 531

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28436
    admin
    Keymaster

    A sprint burndown chart shows sudden progress near the end. What risk does this trend indicate?

    A. Tasks were underestimated
    B. Team ignored definition of done
    C. Work was not continuously integrated
    D. Velocity will likely increase next sprint

    #28439
    admin
    Keymaster

    ✅ Correct Answer: C. Work was not continuously integrated

    🔍 Explanation:
    A. Tasks were underestimated
    ❌ Incorrect. Underestimation would show slow or incomplete progress overall—not necessarily a late sprint spike.

    B. Team ignored definition of done
    ❌ Incorrect. While possible, there’s no direct evidence from the burndown alone. Other metrics or reviews would indicate this more clearly.

    C. Work was not continuously integrated
    ✅ Correct. A sudden drop near the end often means work wasn’t integrated or tested incrementally—violating continuous delivery practices and risking quality.

    D. Velocity will likely increase next sprint
    ❌ Incorrect. Burndown trends don’t predict future velocity directly, especially if the team is not completing work steadily.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    4 PMI-ACP Situational based Practice Tests : PMI-ACP Test Series

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.