✅ Correct Answer: C. Add improvements to the product backlog
🔍 Explanation:
A. Rework the feature in the current sprint
❌ Incorrect. Sprints are timeboxed and not reopened. Work should be done in upcoming sprints based on prioritization.
B. Cancel the next sprint to resolve the issue
❌ Incorrect. Sprint cancellation is rare and drastic—used only when sprint goals are no longer valid. This is not one of those cases.
C. Add improvements to the product backlog
✅ Correct. In Agile, all feedback—even post-review—should go through the product backlog to be prioritized by the Product Owner and potentially included in future sprints.
D. Escalate the concern to senior management
❌ Incorrect. Agile teams are self-organizing. This is a routine feedback scenario that should be resolved within the team, not escalated unnecessarily.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
4 PMI-ACP Situational based Practice Tests : PMI-ACP Test Series
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram