Home › Forums › Agile (PMP/ACP/Scrum) Questions and Answers › Agile Question 53 This topic has 1 reply, 1 voice, and was last updated 4 years, 11 months ago by admin. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts July 2, 2020 at 12:48 PM #6814 adminKeymaster What is not the aim of the WIP limits? a. Optimize throughput of the work b. Optimize resource utilization c. Identify bottlenecks d. Reduce risk of tied-up capital July 2, 2020 at 12:51 PM #6815 adminKeymaster Correct answer is B. WIP limits along with Kanban board helps in reducing the risk of tied-up capital, rework, and optimize throughput of the work. Pass PMI-ACP in the First Attempt : PMI-ACP Strategy All PMI-ACP Question & Answers: Question & Answers Learn Agile Concepts : Agile Concepts Agile Tips & Tricks : Agile Tips & Tricks Quiz: 30 Questions Challenge Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In