Agile Question 529

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #28427
    admin
    Keymaster

    A team has completed 25, 30, 28, and 32 story points over 4 sprints. The Product Owner wants to plan the next 3 sprints using the highest value. What is the best response?

    A. Use 32 points as velocity for all sprints
    B. Use average velocity of the 4 sprints
    C. Use 28 points to allow safe forecasting
    D. Use 25 points as a conservative estimate

    #28430
    admin
    Keymaster

    ✅ Correct Answer: B. Use average velocity of the 4 sprints

    🔍 Explanation:
    A. Use 32 points as velocity for all sprints
    ❌ Incorrect. This represents the highest velocity, not the most consistent or predictable. It may lead to overcommitment and missed sprint goals.

    B. Use average velocity of the 4 sprints
    ✅ Correct. Average velocity gives a balanced view of the team’s performance over time and is the most reliable measure for forecasting.

    C. Use 28 points to allow safe forecasting
    ❌ Incorrect. While 28 is close to the average, selecting it arbitrarily introduces bias. Use actual average for objectivity.

    D. Use 25 points as a conservative estimate
    ❌ Incorrect. Though conservative, it underutilizes team capacity and could slow down value delivery unnecessarily.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.