    During the fifth sprint of a project, the Scrum Team has conducted retrospectives regularly. However, a senior stakeholder complains that while the team is completing work, the same technical debt issues and handover delays continue sprint after sprint. The team acknowledges the patterns but feels there isn’t time to act on retrospective items. As the project manager, what should you do?

    A. Ask the team to document action items in a shared tracker
    B. Allocate buffer time in sprints for improvement activities
    C. Escalate the issue to the Scrum Master to enforce follow-up
    D. Encourage the Product Owner to prioritize only deliverables

    #28418
    admin
    Keymaster

    ✅ Correct Answer: B

    🔍 Explanation:
    ❌ A (Incorrect): Documenting issues helps visibility but does not ensure action or time to resolve them.

    ✅ B (Correct): Allocating buffer or capacity for improvement actions reflects Agile principles of continuous improvement. It directly enables the team to resolve persistent issues.

    ❌ C (Incorrect): Escalation may address symptoms but disempowers the team and bypasses ownership.

    ❌ D (Incorrect): Focusing only on deliverables neglects technical debt and undermines long-term sustainability.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.