Correct Answer:
C. Hold regular sprint reviews with stakeholders
Explanation:
A. Share a status report every sprint
❌ Incorrect – While status reports provide updates, they are passive and do not promote two-way engagement or feedback from stakeholders, which is vital in Agile.
B. Invite them to daily stand-up meetings
❌ Incorrect – Daily stand-ups are meant for the team to synchronize. Involving stakeholders daily can be inefficient and distract from team autonomy.
C. Hold regular sprint reviews with stakeholders
✅ Correct – Sprint reviews are designed for stakeholders to see progress, provide feedback, and collaborate with the team. This keeps them engaged and ensures alignment with evolving goals.
D. Escalate concerns to the sponsor immediately
❌ Incorrect – Escalation should be a last resort. Agile encourages direct collaboration and regular feedback loops rather than immediate escalation.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram