✅ Correct Answer: B. Velocity
🔍 Explanation:
A. Lead Time
❌ Incorrect. Lead time measures the time from request to delivery. It’s useful for understanding flow but not ideal for sprint-level forecasting.
B. Velocity
✅ Correct. Velocity measures the amount of work completed (often in story points) in each sprint. It helps the team forecast future work capacity and plan upcoming sprints effectively.
C. Cycle Time
❌ Incorrect. Cycle time is the time it takes to complete a task once work has started. It’s useful for analyzing efficiency but not directly for sprint planning.
D. Burn Rate
❌ Incorrect. Burn rate refers to how fast budget is being spent, which is a financial metric—not specific to measuring work done per sprint in Agile.
Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel
Pass PMP in the First Attempt : PMP Strategy
Pass PMI-ACP in the First Attempt : PMI-ACP Strategy
All PMP/ACP Question & Answers: Question & Answers
Revise PMP & Agile Concepts: PMP/Agile Concepts
PMP Tips & Tricks: PMP Tips & Tricks
Agile Tips & Tricks : Agile Tips & Tricks
PMP & ACP Quiz:
20 Questions Challenge 50 Questions Challenge
Study Groups: Facebook Whatsapp Telegram