    A team wants to measure how much work they complete each sprint to help with forecasting. Which metric should they use?

    A. Lead Time
    B. Velocity
    C. Cycle Time
    D. Burn Rate

    #28406
    admin
    Keymaster

    ✅ Correct Answer: B. Velocity

    🔍 Explanation:
    A. Lead Time
    ❌ Incorrect. Lead time measures the time from request to delivery. It’s useful for understanding flow but not ideal for sprint-level forecasting.

    B. Velocity
    ✅ Correct. Velocity measures the amount of work completed (often in story points) in each sprint. It helps the team forecast future work capacity and plan upcoming sprints effectively.

    C. Cycle Time
    ❌ Incorrect. Cycle time is the time it takes to complete a task once work has started. It’s useful for analyzing efficiency but not directly for sprint planning.

    D. Burn Rate
    ❌ Incorrect. Burn rate refers to how fast budget is being spent, which is a financial metric—not specific to measuring work done per sprint in Agile.

    Tips/Tricks/Cheatsheet to master PMP/ACP Exam and Concepts : Youtube Channel

    Pass PMP in the First Attempt : PMP Strategy

    Pass PMI-ACP in the First Attempt : PMI-ACP Strategy

    All PMP/ACP Question & AnswersQuestion & Answers

    Revise PMP & Agile ConceptsPMP/Agile Concepts

    PMP Tips & TricksPMP Tips & Tricks

    Agile Tips & Tricks : Agile Tips & Tricks

    PMP & ACP Quiz:
    20 Questions Challenge 50 Questions Challenge

    Study Groups: Facebook Whatsapp Telegram

Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.